Chile’s data center sector confronts a critical infrastructure mismatch as projects totaling approximately 2 GW seek grid connections while electrical network expansion timelines lag project construction by up to two years. Two new 500 MW proposals from Ignis Energy Chile and Lader Energy Chile underscore mounting pressure on transmission capacity concentrated in Santiago and Valparaíso, where installed facilities currently represent just 407 MW connected between June 2020 and May 2026. The disconnect between 9-12 month data center construction cycles and 24-36 month electrical connection processes threatens to constrain Chile’s positioning as a regional digital infrastructure hub despite favorable renewable energy availability.