Engineer Roberto Vernet reported that Venezuela’s National Electric System operates with a 3,900 megawatt deficit while thermal generation reaches only 2,800 MW, as lack of maintenance has left 80 percent of installed thermal capacity offline. The shortfall intensifies following a 1,200 MW loss at the Guri hydroelectric complex in late August, with repair timelines extending at least two years and accumulated failures potentially pushing the total deficit to 2,500 MW during peak demand hours.